During half term we were asked to complete an emergency installation for Eaton Hall

Specialist Academy. Eaton Hall is part of the Right for Success Academy Group for whom we have undertaken projects for Sewell Park Academy, Sprowston Academy, Tuckswood Academy, Martham Academy, Stalham Academy and St Clements Free School.

Eaton Hall is the only Norfolk specialist academy catering for students with social, emotional and mental health difficulties. The school is residential and operates with a 24 hour curriculum.

The school’s cabling infrastructure was in serious need of replacement and due to various security issues the academy felt that they had to act. Eastern Voice & Data had anticipated that the project would be completed during a longer holiday break and had estimated that 3 weeks would be required to fully complete the project. The amount of work required was further complicated by the need to replace the main security gate that had been damaged in a collision with a truck. This involved groundwork to lay an armoured fibre optic cable so that a video access system could be installed. The existing telephone system was no longer fit for purpose and a school wide DECT system was specified allowing staff to be able to call for assistance.

Eastern Voice & Data specified an updated network solution utilising ZyXel Gigabit switches. This was allied to a Panasonic NS700 IP-PBX that provided full cordless coverage over the whole site by virtue of networked Panasonic IP DECT Base stations and KXTCA185 DECT Handsets. SIP trunks provided a managed fibre optic voice connection to complete the telephony set up.

The door entry solution was provided by 2N, consisting of a vandal resistant IP Force video intercom networked to the school reception via a secure fibre optic connection allowing school staff to view visitors and converse with them. The wifi control panel also provided a video memory log of all callers to the site.

The students left for half term on the 18th and 6 engineers immediately began to strip out the existing network and telephone system. Groundworks for the installation of the new security gate and fibre optic connection started on the 22nd. By the 26th the cabling infrastructure had been replaced, a total of 12 DECT base stations newly installed providing full site coverage, new ZyXel network switches had also been installed. By the 29th the new security gate installation was complete and the fibre optic connected.

An installation that effectively completely replaced the entire IT network, telephone system and secure door entry was complete in 8 days from project start to completion.